Weed spraying schedule

Spraying is dependent on good weather conditions and can't take place during high winds or wet weather. Dates may change.

We have found that weeds treated with Nomix Dual take around 3 to 4 weeks to die off after treatment.

Ward Planned Start Date Actual Start Date Planned Completion Date Actual Completion Date  
Birkenhead & Tranmere 23-Apr 23-Apr 24-Apr 29-Apr  
Seacombe 28-Apr 29-Apr 28-Apr 01-May  
Liscard 29-Apr 02-May 30-Apr 06-May  
New Brighton 01-May 07-May 01-May 12-May  
Wallasey 05-May 12-May 05-May 20-May  
Leasowe & Moreton East 06-May 20-May 06-May 22-May  
Moreton West & Saughall Massie 07-May 22-May 07-May 26-May  
Bidston & St James 08-May 26-May 08-May 06-Jun  
Upton   16-Jun 15-Jun 24-Jun 30-Jun  
Claughton  09-Jun 09-Jun 12-Jun 16-Jun  
Oxton  15-Jun 16-Jun 16-Jun 19-Jun  
Prenton 09-Jun 09-Jun 15-Jun 19-Jun  
Rock Ferry 16-Jun 22-Jun 18-Jun 24-Jun  
Bebington 18-Jun 25-Jun 22-Jun 30-Jun  
Bromborough 01-Jul   06-Jul    
Eastham 07-Jul   09-Jul    
Hoylake & Meols 10-Jan   14-Jul    
West Kirby & Thurstaston 13-Jul   15-Jul    
Greasby, Frankby & Irby 15-Jul   17-Jul    
Clatterbridge 16-Jul   21-Jul    
Pensby/Thingwall  20-Jul   22-Jul    
Heswall 23-Jul   27-Jul    
Alleyways 09-Apr 09-Apr 15-Jun 15-Jun  